Verifying an as-built panel count against an interconnection capacity milestone

High-angle view of rows of pole-mounted solar panels installed on a grassy field

An interconnection agreement rarely ties a draw to "percent complete." It ties it to a capacity number: so many MW of nameplate DC capacity mechanically installed and ready for the next interconnection study milestone, or ready to energize. The EPC's monthly report says 72% installed. Nobody on the lender's side can tell from that sentence whether the site actually has enough modules racked to clear the MW threshold in the agreement, or whether the EPC rounded up because the schedule is slipping and the next draw is due.

The gap between those two things, a percent-complete narrative and a capacity number tied to a legal milestone, is where a lot of draw disputes start.

Turning a module count into a capacity number

Nameplate DC capacity is just arithmetic once you have a real count: module wattage times number of modules installed, divided by a million for MW. A site built with 550 W modules needs about 2,000 modules on racking to hit 1.1 MW DC. If the interconnection agreement's milestone is "50% of nameplate DC capacity mechanically complete," the lender's question collapses to one number: how many modules are physically on the tables and wired, this week, at this site.

That number has to come from somewhere other than the EPC's own progress report. A construction monitor can walk a few rows and extrapolate, which works until the site is 40 acres and the schedule is tight. A drone survey flown once gives a point-in-time count but doesn't answer what happens next quarter when the draw request comes in again.

An as-built module count taken from wide-area imagery and cross-checked table by table does the same arithmetic the lender already trusts, module wattage times count, without relying on the EPC's own percentage. That's the role Solar Panel Counting is built around: a counted inventory of modules, tables and inverters at the site, delivered from very high resolution imagery each quarter, so the number behind the milestone comes from an independent source rather than the contractor being paid against it.

Reconciling the count against the draw schedule

The practical check runs in three steps, whether it's done by a construction monitor on site or against imagery:

  1. Pull the milestone language from the interconnection agreement or the draw schedule. It usually specifies a capacity threshold, not a module count directly, so convert it using the project's module wattage.
  2. Count what's actually installed and wired. "Installed" for this purpose generally means racked, connected, and part of a completed string. Boxed modules staged on pallets near the substation belong to the contract value line, separate from the capacity milestone itself.
  3. Compare the converted module count against the agreement's threshold and flag the delta. A site at 1,850 of a required 2,000 modules isn't at milestone yet, whatever the EPC's progress report says.

The part that trips people up is step two. A module count from a satellite or aerial pass at resolution fine enough to distinguish individual panels (well under half a meter per pixel) can tell racked-and-wired modules from stacked pallets and from modules sitting on the ground awaiting mounting. A monthly photo log from the EPC usually can't make that distinction reliably, because it's shot from angles the EPC chooses and at a cadence the EPC controls.

Where this fits in the draw cycle

None of this replaces the construction monitor's report or the independent engineer's certificate. It gives both of them a number to check against: an as-built module count, tied to the site's actual nameplate math, refreshed on a cadence that lines up with quarterly draws rather than a single pre-funding site visit. When the EPC's percent-installed and the counted inventory agree, the draw goes through on schedule. When they don't, the lender has a specific, countable reason to ask for more before releasing funds.

If your interconnection milestones are written in MW and your EPC's updates are written in percentages, an independently counted module inventory closes that gap every quarter without anyone needing to walk the rows themselves.